Tuckpointing Stage2 Benton Project Warehouse Walls

Tuckpointing- Its not as glamorous as the carpentry aspects of my profession. But it is just as important and since St Louis has so many brick buildings it is a must have skill!


The above photo shows the mortar joints grinded out 1/2in or more deep. This will allow the new mortar pointed into the joints to fully adhere to the brick and give the Masonry Wall another 100+ years of Life!








Read More on the Benton Rehab Stage 2 Construction Project:

Thank you for stopping by St Louis Renewable Energy. Feel free to comment in the section below or contact Scotts Contracting- St Louis Home Improvement Projects and Energy Reducing Needs Get Your Green Building Tips and Resources at St Louis Renewable Energy Green Blog

4.27.2013

Benton Rehab Tree Root Experiment and Damage Update

Day 5 in the Benton Rehab Roof Project uncovered some interesting hidden gems in the roof system.  In the photos below you can view the extensive tree Stump and Root Ball that started out as a sapling years ago and was left to its own accord.

Benton Rehab Tree Root Experiment-How Far Did the Roots Grow when left unattended?



damage this little tree was causing to the adjacent 4 Family Unit. Benton Rehab Project



Experiment to see how far a tree root will grow when left unattended for 10 plus years.  Benton Rehab Roof Project

The photo is of the tree's root ball that was growing in the built up roof system.  While this was not the only culprit as to the roofs demise in the past 10 years it has led to the steady degradation of the roof system.

Note: Part of the reason we left this tree and root system intact was so that we could trace the roots to ensure it was removed completely from the wall and roof system-eliminating a tree restarting from its roots.  Its also part of an:


Experiment to see how far a tree root will grow when left unattended for 10 plus years.

Note Added May 1st 2013- I found a tree root growing down into this section of wall yesterday.  I believe the tree root started this crack in the wall long ago and as the Invasive Tree Root grew it widened the crack in the wall.  When we replace this section of the wall.  We will find out more.  Stay Tuned for further updates.

This last photo was included to show the before tuckpointing the parapet wall. [And the saplings that are attempting to gain a foothold] Required step before installing the new roof system of: Bar Joists, Pan Decking, and Concrete Topping.

Photos added May 1, 2013

Additional Tree Root Photos and the Damage They Caused
We traced the Invasive Tree Root for another 10 Feet and found the tree root had followed the top course of Masonry alongside the Parapet Wall.Benton Rehab Project
We traced the Invasive Tree Root for another 10 Feet and found the tree root had followed the top course of Masonry alongside the Parapet Wall.
I did not actually measure the Tree Root and am going to venture to say the Invasive Tree Root had grown to a distance of 15-20 feet in length and followed the top course of brick alongside the Parapet Wall.

Additional Benton Rehab Stage 2 Project Green Blog Postings




Thank you for stopping by St Louis Renewable Energy. Feel free to comment in the section below or contact Scotts Contracting- St Louis Home Improvement Projects and Energy Reducing Needs Get Your Green Building Tips and Resources at St Louis Renewable Energy Green Blog

4.26.2013

Benton Roof Project Daily Report

On Day 4- The Crew and I have the first dumpster filled and ready for pick-up and 75% of the Roof has been removed as seen in the photo taken 1pm on Thursday.


In these photos you can see the I Beams that will be utilized to hold the Bar Joists and Pan Decking for the New Roof System.


Thank you for stopping by St Louis Renewable Energy. Feel free to comment in the section below or contact Scotts Contracting- St Louis Home Improvement Projects and Energy Reducing Needs Get Your Green Building Tips and Resources at St Louis Renewable Energy Green Blog

4.25.2013

Benton Project Stage 2 Dismantling Roof Demolition

Stage 2 Benton Rehab Warehouse Roof-Before Photo
Stage 2 Benton Rehab Warehouse Roof-Before Photo
With the Dumpster delivered and parked in the bay the crew has started removing the roof-despite the rain StLouis has been getting as of late.

We estimate the Roof we are removing was 50 years old and was originally a rock ballast roof system with an additional 4-5 layers of patching.

Tearing Off the Existing Roof-Stage 2 Benton Project
Tearing Off the Existing Roof-Stage 2 Benton Project

Tearing Off the Existing Roof-Stage 2 Benton Project
Tearing Off the Existing Roof-Stage 2 Benton Project

Parking the Dumpster in the Warehouse Bay we estimate will save 1 days worth of  Labor for the Crew and makes our lives much easier for the roof tear off!
Parking the Dumpster in the Warehouse Bay we estimate will save 1 days worth of  Labor for the Crew and makes our lives much easier for the roof tear off!


Despite the Rain the Crew is making good progress with removing the existing roof with 1/4 to 1/3 of the old roof removed.

See additional photos of the project at Google Plus






Thank you for stopping by St Louis Renewable Energy. Feel free to comment in the section below or contact Scotts Contracting- St Louis Home Improvement Projects and Energy Reducing Needs Get Your Green Building Tips and Resources at St Louis Renewable Energy Green Blog

Connect with Scotts Contracting

FB FB Twitter LinkedIn Blog Blog Blog Blog Pinterest

Featured Post

1 Hack To Eliminate Your A/C Power Bill This Summer!